Summary
The worst stretch of 11 Mile — including in front of Lakeview High School — gets a $498,256 patching contract with Florence Cement this summer, timed between the end and start of the school year with liquidated damages if they run late.
At a glance
- Total mentions
- 2
- Last 30 days
- 0
Discussed at 1 meeting in the last 60 days; most recently Sep 21, 2026.
Impact analysis
$498,256 total project award from the Major Streets fund.
Lakeview High School students and every driver on that battered stretch of 11 Mile.
Drivers face temporary lane closures along 11 Mile during summer construction.
Mentions & discussions (2)
City Council - Sep 21, 2026
The rush job in front of Lakeview High School finished before school started, but cost $120,000 more than bid after engineers estimated 7 failing catch basins and found all 35 shot. The council approved paying for work already done but is making the westbound half go out to competitive bid.
City Council - Jun 1, 2026
The worst stretch of 11 Mile — including in front of Lakeview High School — gets a $498,256 patching contract with Florence Cement this summer, timed between the end and start of the school year with liquidated damages if they run late.
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for St. Clair Shores
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.